Murchison Zinc Company Pty Ltd – Optimisation Study for Golden Grove.

Minproc – Consultant Project Engineer undertaking feasibility studies including mining reserves, scheduling, conceptual layouts, mine rehabilitation proposals, mine management structures and costs on alluvial and hard rock/gold mining projects throughout Australia.

Minproc – Consultant Project Engineer responsible for the initial site location studies in the Environmental Impact Statement required for Minproc Holding’s sodium cyanide plant in Gladstone.

Minproc – Consultant Project Engineer providing assessment of the infrastructure requirements for Pancontinental Mining’s Thalanga and Lady Loretta deposits in Queensland.

Hamersley Iron Pty Limited – Senior Mining Engineer responsible for long term planning of the Paraburdoo Orebody including the introduction of the 4 West Deposit, mine scheduling, mine layout, major new mining equipment recommendations and project infrastructure.

Minerals Mining and Metallurgy Limited – Surface Mining Manager responsible for planning, development and operation of the Blackwoods opencut and ongoing dump treatment operations including rehabilitation of the surface area of the mine.

Minerals Mining and Metallurgy Limited – Surface Mining Manager, feasibility studies on Blackwoods Opencut, and underground projects including development of the Western Mineralisation in Broken Hill.

North Broken Hill Limited – Mining Engineer, assisted in the development of the Silver Peak Deposit north of Broken Hill.